NHS IT project delays hurt BT and CSC

BT and CSC paid only 40% of contract after late delivery

NHS IT suppliers have been paid so far only 40 per cent of projected amounts on the £12.7 billion National Programme for IT.

The news emerged as the NHS suppliers said they were confident they were successfully rolling out the first workable patient systems this month, in time for a deadline imposed earlier this year by the programme’s new chiefs.

The government yesterday said it will cost £6.4 million per hospital, across most of England, to simply implement the systems.

Suppliers have been paid only £2.7 billion under their contracts so far, out of an originally projected £6.7 billion, on a programme that was originally due for completion by next year.

The reason for the payments being lower than original projections is that suppliers are only paid on delivery, and delivery has been delayed after a number of problematic rollouts.

The government’s spending auditors said last year that the programme will run until at least 2014 to 2015.

As of 31 March, CSC, supplier to the North, East and Midlands, had been paid £784 million out of its £3 billion contract, according to figures released by health secretary Mike O’Brien. Last week it switched on the first full instance of the iSoft Lorenzo patient software in NHS Bury.

BT, whose Global Services devision has been hit hard financially by work on the programme, has been paid £326 million for rolllouts in London, compared to an original expectation of £1 billion. It expects to go live with the equivalent Cerner Millennium patient system in the next three weeks at NHS Kingston.

Both suppliers are under pressure to make sure the system in those two trusts satisfies the NHS when it conducts a review at the end of the month. Failure by either could result in contract termination.

In the south of England, previously covered by Fujitsu, until it pulled out in Spring 2008, some £326 million has been spent, compared to the £1.1 billion predicted. BT now runs a number of trusts in the south, but others are still looking for a new contractor.

Tola Sargeant, research director at analyst house TechMarketView, told Computerworld UK that she was “not surprised” the figures are so far below original predictions, after the delayed rollouts.

Whilst it was “good news for taxpayers” in the short term, she said, it also demonstrated delayed delivery. The figures were “not good” for suppliers BT and CSC, she noted, adding that they would have to deliver the systems “in earnest”. They showed "just how important it is for the two remaining LSPs to meet the crucial deadlines set by the NHS and ramp up deployment in 2010", she said.

Other parts of the programme, not involving deployment of the patient administration systems, are more close to financial expectations.

For the ‘spine’, which is the central network bearing the patient data, contractor BT has been paid £791 million, which is the majority of the contracted £889 million, indicating more timely deplooyment in this area.

The NHS’ Choose and Book appointments system, delivered by Atos Origin, has cost £133 million, out of a predicted £144 million, and the completed N3 broadband network, delivered by BT, cost its predicted £554 million.

A spokesperson at the Department for Health said the government will "consider" producing an annual report of NHS IT progress against timetables and expenditure forecasts, in response to demands from the Commitee of Public Accounts. An annual report may be combined with updates on benefits delivered, it said, but there are no definite plans.

Registration is free, and gives you full access to our extensive white paper library, case studies & analysis, downloads & speciality areas, and more.

Earlier this year, the NHS said that if it is not satisfied that BT and CSC have delivered workable patient systems by the end of this month, it will reconsider how to deliver the programme or even cancel supplier contracts. Both CSC and BT have said they are confident the NHS will be satisfied with them in its review.

But there are also suggestions by industry observers that the late delivery, and under-expenditure so far, could present a 'get-out' for Whitehall. Sargeant at TechMarketView issued a stark warning that a "cash-strapped government" could be tempted "to try to claw back some of the funding by curtailing the programme".



Email Updates

CIO Newsletters: Expert insight, advice and tools for technology, business, leadership and the CIO career.


Email this article to a friend or colleague:


PLEASE NOTE: Your name is used only to let the recipient know who sent the story, and in case of transmission error. Both your name and the recipient's name and address will not be used for any other purpose.


CIO White Papers

Legal risks of uncontrolled email and web use

Exploring the challenges facing IT Mangers today and vital steps to ensure safe internet an email use by employees.

The challenge of strategic alignment

Recent research also shows that many organisations give too much prominence to internally generated KPIs – controlling the controllable – rather than looking outwards at threats and opportunities on the horizon which can ultimately be far more influential on performance.

Six essential steps to successful IT centralisation

This report, based on the real experience of a recent centralisation project, is aimed at those involved in IT strategy within their organisation. It provides some practical insights for CIOs, CTOs, Heads of IT, IT Directors and those involved more closely with the service management function.

Managing email: Exploring common email management challenges (and how to overcome them)

We surveyed 157 IT professionals to understand the difficulties and opportunities faced by email managers. From this we were able to highlight some easy-to-manange solutions to their most pressing problems.


CIO UK - Business - Technology - Leadership

Differentiate your company with complete CRM

Focused on productivity and empowerment and leveraging the natural rhythms people work
What defines Complete CRM? How businesses can better engage customers and users, manage customer transactions, and analyse results to adapt and take advantage of changing business and economic circumstances.

DOWNLOAD

Oracle White Paper

IT Misuse Survey

Complete this survey and you could win a Nexus One.

CIO are running a short survey to discover how UK businesses are managing internet and email misuse in the Enterprise.

COMPLETE SURVEY

Virtualisation - The 'black hole' of security?

Covering the set of issues, ideas and perceptions discussed during a recently held debate about the effect of virtualisation techniques on organisational security. This paper provides a comprehensive account of all the subject matters debated and concludes with key takeaways and IDC recommended actions.

DOWNLOAD

Trend Micro



* *